Update August 2008.
Work continues to progress on the highly anticipated Coastal Highway (Carretera Costera). The 83 miles segment linking El Golfo to Rocky Point is still between 85% and 90% complete. Progress is slow but it is still progressing. There is around 46km from Rocky Point towards El Golfo and another 50+km heading from El Golfo towards Rocky Point and a section in between as well that is complete. The entire length of the freeway has been surveyed and staked with most of it having the first excavation preformed. There are many more km with the subsurface complete and new asphalt is being added daily.
All of the pictures on the left side of this page are expandable by clicking on them.
Return here each month and we will do our best to update you on the progress or signup for the monthly newsletter.
You can now also follow the progress of the new proposed International Airport by clicking on this link.